Warsaw Railroad Work Will Continue Into Next Week
WARSAW — Norfolk Southern plans to pave Market Street on Monday, July 2, and reopen it to traffic that same day.
CR 250N and CR 350N will close on Sunday, July 1, as the gang progresses northward. Both crossings are expected to reopen sometime on Monday, July 2, after paving is completed and cooled later in the day.
Levi Lee Road may be closed sometime on Monday, July 2, but it is more likely to close on Tuesday, July 3.
The dual rail gang will not work on Wednesday, July 4, due to the holiday, so Tuesday, July 3, will be their last work day for next week.