AKRON — The Tippecanoe Valley High School construction project is mainly down to punch list items.
At its monthly public work session at TVHS on Thursday, Nov. 14, the Tippecanoe Valley School Board heard the above news from The Skillman Corp. Project Manager Scott Rogers.
The Skillman Corp. is the construction management company for the project.
Parts of the project left include the auditorium and the wrestling and multipurpose room.
Rogers said some aisle lights for the auditorium should be in on Saturday, Nov. 16, with workers to put them in starting on Monday, Nov. 18.
“We’re trying to work around that schedule for (TVHS’ fall play ‘Circus Olympus’),” he said.
That play is Thursday, Nov. 21, and Saturday, Nov. 23.
The carpeting in the auditorium should also be finished by next month.
Rogers noted flooring in the wrestling and multipurpose room “just got finished today.”
He and Tippecanoe Valley School Board Superintendent Blaine Conley said the construction project probably will go into December.